hi all,

can we use the plann strategy 52 - plann w/o final assmbly w/ mto in the repetitive mfg.

since it create the production order after the sales order comes.

pls clear me

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Oct 15, 2008 at 10:36 AM

    Dear,

    Yes we can use it in REM.

    Planned order type VP, you can not convert. This is created when you use strategy 52 or 50

    These strategies are Make to Order. If you create PIR for this material, after MRP run system will create planned order with Order type VP. This planned order can not convert to production order. After getting sale order, it will consume the PIR. Now system will allow to process further this planned order.

    Please refer this thread for details ,

    planning-strategy-52reg

    Regards,

    R.Brahmankar