Creation of Multiple Activities for same Employee,same day and same time

Hi Experts,

In CRM 2007 I am creating an Activity(e.g Customer Visit) for a particular day for a particular employee. I am selecting the Option "Whole Day".

When again I am creating another Activity same day and for same employee the ideally system should not allow me to create further activities as I have already scheduled for the whole day but its is allowing me to create as many activities i want irrespective of Time frame.

I want to block overlappped activities created for same emloyee same time.

Can you please suggest me with your ideas inorder to achieve same???

Regards

Arup

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Oct 18, 2008 at 07:07 AM

    Hi Experts,

    Any more solution to this???

    Regards

    Arup

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 15, 2008 at 12:32 PM

    Hello,

    If there is no standard solution you can implement the BADI : CRM_ORDERADM_H_BADI

    Here you can see when a new activity is created, and then maybe you can cancel the creation or even replace the new activity by the existing one.

    Regards,

    BenoĆ®