Funds Management related error while creating Purchase Requisition

Hi,

Am working in ECC6.0 system with Funds Management integration. While creating PR am getting below mentioned error

"At least one GL account was not derived by the budgetary ledger

Message no. FI_E034"

Diagnosis

You are using the Funds Management system integrated with the budgetary ledger (BL) active for FM area .

Postings into the budgetary ledger require a GL account for each of the budgetary ledger line items. However,

in this case, at least one of the line items in the BL interface table does not contain a GL account.

Use the link below to analyze the table contents before and after the account derivation process.

Budgetary ledger account derivation trace

System Response

The budgetary ledger cannot post this document. The BL document"

Can some body guide me how to fix this error.

Thanks in advance

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Oct 15, 2008 at 05:07 AM

    hi

    which component you are using?

    FORMER BUDGETING OR BUDGET CONTROLSYSTEM( BCS)

    CHECK YOUR DERIVATION STRATEGY BY USING FMDERIVE.

    CHECK DERIVATION RULE FOR BUDGETERY LEDGER AND G/L ACCOUNT.

    THANKS & REGARDS

    MALA K VUNDELA

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 15, 2008 at 05:14 AM

    Hi Mala,

    We are using BCS.

    Can you guide me where to check "CHECK DERIVATION RULE FOR BUDGETERY LEDGER AND G/L ACCOUNT"

    Thanks

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 21, 2008 at 11:15 AM

    Hi,

    Do you have budget ledger activated? Is this on purpose or by mistake?

    Regards,

    Eli

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.