Dear Team,

I would like to know how below figure is calculated(circled in red) for CNE5 Progress analysis. i.e. 36.35, 17.23 and 43.66. The figure highlighted in yellow are from activity confirmation

I am using the degree of processing as progress method and defined POC weight for each WBS. POC weight is shown in last column. I have done cost element planning for both WBS 1 and 2. Also, plan revenue maintained for higher level WBS.

Kindly advise me, how these WBS POC figures are calculated.

Regards,

Atul Rajmane



Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hello, Atul! Did you find an answer for yr inquiry? I have the same question. If you found out and could share here, it would be much appreciated. Thank you, Patricia.