Hi

I need PR Release Stgy at item level.

If i hv a PR with 10 line items, I want to release one by one line as per my requirement.

How to acheive this?

Regards

Ram

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 14, 2008 at 10:27 AM

    Dear,

    With classification

    With this procedure, requisitions can be released both at item level (i.e. item-by-item) and in total. The latter approach is also termed "overall release".

    Without classification

    With this procedure, requisitions can only be released at item level.

    Go through the link content at : http://www.scribd.com/doc/548510/SAP-Release-Strategy

    Regards,

    Syed Hussain.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi

      I hv configured all SPRO with respect to without classification.

      But still i cant release the PR. Error coming is PR ........... can not be released.

      Vijay

  • Oct 14, 2008 at 10:28 AM
    Add comment
    10|10000 characters needed characters exceeded

  • Oct 14, 2008 at 10:40 AM

    Hi

    Goto SPRO>MM>Purch>PR>Release procedure>Prcedure with classification>Setup Prcedure with classification> Double click release groups>Remove the tick in checkbox (means items are release individually)

    Regards,

    Baskar