Schedule Maintenance Plan using IP02

Apr 23 at 10:40 AM

30

avatar image
Former Member

Hi,

We have this request from the business to schedule Maintenance Plan using IP02. The buttons for release call, fix call, etc is greyed out in the IP02. Is there a way to activate this? Can we implement a SAP Note or use any user exits that will enable this?

Thank you.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Maria Terence Apr 23 at 10:55 AM
0

Hi,

To Schedule, You need to use IP10 and for deadline Monitoring (Batch Job) use IP30

IP02 is for changing the maintenance plan

Regards

Terence