Production Error

I am able to set a production run from u201Creleasedu201D to u201Cclosedu201D without the cycle being completed. I have proven that this is possible but Iu2019m not sure why SAP allows that. So in effect, I can issue to production then close the order and now have a misstatement in my WIP account? How can I fix?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 13, 2008 at 06:28 PM

    Paul,

    A production order when in a Released state can be cancelled as technically the production has not started.

    When you have Issued components the Inventory raw materials gets reduced and the WIP account in increased..correnponding JE would be

    Inventory WIP Dr

    Inventory Raw Mtrl Cr

    At this stage if you manually close the Production Order...there is a JE created to represent this..

    WIP Material Variances Dr

    Inventory WIP Cr

    I am not sure why you feel that the WIP balance still stays....I believe the G/L Account mapping is incorrect in your company database

    The WIP Material Variances account is generally defined in the Cost of Goods drawer....please check this and make the necessary changes in the G/L determination (WIP Inventory Variance Account)

    Suda

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 13, 2008 at 04:44 PM

    Hi Paul,

    In the business world, there are so many different processes that are not Normal. Simply block some those functions may not work.

    In order for you to block the production being closed from released status manually, you can use SP Transaction Notification.

    Search this forum to find many examples of this SP.

    Thanks,

    Gordon

    Add comment