Planned Revenue not flowing to projects

Dear All

This is a T&M project scenario. Billing based on manhours

Here my planned revenue (Sales order price) from sales order is not updating in project. Actual cost is updating from project to sales.

Can anybody help me to solve this

Regards

Deepu Pillai

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

8 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 13, 2008 at 11:33 AM

    Hi

    Check the setting in planning profile you are using. T code OPSB, Automatic revenue planning tab. "From sales order " check box should be ticked.

    Regards

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear,

      I m also having same probleb ,i've checked the setting in planning profile and its ticked as automatic revenue planning from sales order.

      If the revenue element which i've inserted in profile is effecting the revenue report.

      And also the after down payment the payment value also not showing in CN41.

      Regards.

  • avatar image
    Former Member
    Oct 15, 2008 at 10:11 AM

    Hi

    Pl see if the values are gettinbg updated in revenue planning transaction CJ42, version:00, under column heading "sales order value". If the values are getting updated here, then the issue could be juest a reporting issue.

    Pl revert

    regards

    Murali

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear Sir,

      Its not getting updated in CJ42.

      if this is releted to cjvc revenue element.

      Its traffic light is red in CO area.

      Regards.

      Sukhveer.

  • avatar image
    Former Member
    Oct 15, 2008 at 09:43 AM

    dear,

    Problem is still there Sales order value is not showing under revenue planning in WBSE.

    So please do't close these thred

    Need help from experts.

    Regards.

    Sukhveer.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 15, 2008 at 11:19 AM

    Hi,

    I do think it is related value category customization (OPI1 & OPI2) . Pl check whether value categories are assigned to the correct cost element range / group as well as whether revenue / cost categorization in OPI1 is proper.

    Murali

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 13, 2008 at 11:55 AM

    Hi,

    Make sure following settings

    1-go to OPSB and tick FROM SALES ORDER indicator in

    automatic revenue planning tab.

    2-go to OKKP and choose component active for order management.

    and tick SALES ORDERS indicator.

    Regards,

    Vivek tripathi

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Dear,

      Sorry i've not able to check your mail.

      This report is not created in my company

      S_ALR_87013564 i'll send to SAP and get NOTE or Patch.

      In CJVC status of CO Area is RED Status but the

      Revenue element is status green .

      Is there any problem for that status.

      Cost element is of catagory 11.

      assignment to WBSE is correct.

      Do't know the use of cjvc.

      Regards.

  • avatar image
    Former Member
    Oct 14, 2008 at 05:48 AM

    HI

    IF all settings told by venket r correct , then check accounting document generated by sales order.

    check g/l account and sd integration is correct .

    shashank

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 14, 2008 at 05:58 AM

    Hi,

    Most likely account determination is not happening in sales order on account of wrong / inadequate G/L account assignment. You can check this in sales order as below:

    VA02->Environment->Analysis->Account Determination.

    Pl see whether G/L accounts are detrmined properly.

    If there is a problem here (most likely, yes), assign proper G/L accounts in SPRO transaction as below:

    SPRO->Sales & Distribution->Basic Functions->Account Assignment/ Costing->Revenue Account Determination->Assign G/L accounts.

    If you are not familiar with customization of this, you may like to take the help of a SD/FI consultant.

    Murali

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 16, 2008 at 03:55 PM

    Hi,

    I would recommend to check this in debugging.

    Set a breakpoint in function module K_PROJECT_SD_PLANVALUES at the following line:

    ...

    • Fill internal tables from interface table

    perform tcoeri_fill_from_acctsd tables t_acctsd. <<<<

    Make a change to the sales order (changing PO number) and save it.

    In table T_ACCTSD you will see, what is transferred from SD to PS. Please check fields SAKNR and FKDAT.

    Often the problem is, that the cost element is not valid at the posting date (FKDAT).

    The relevant checks are done in include LKAOVF01 (subroutine COERI_FILL_FROM_ACCTSD). Only the data, that is transferred to table T_COERI can be posted as planned revenues on PS side.

    If there is no useful data in T_ACCTSD at all, this is a SD topic. There might be a problem in account determination or other.

    Please read notes no. 96404 and 647261.

    Best regards,

    Gerald.