Item Category 'TAB' - Individual PO scenario

Hi, can anyone advise how SAP derive the schedule line delivery date for item cat 'TAB'? When i switched the item cat from 'TAB' to 'TAB', system automatically propose a delivery date. However, even if i set the planned delivery time and GR processing of material in master as '0', the delivery date/material availability date for that schedule is still not current date (i set all lead time in SD to be zero as well e.g pick time, load time and transit time). I shd see the delivery as current date since there is not lead time.

Is there some setting i need to do or other master data controlling the delivery date in the SO schedule line for TAB scenario?

Thanks

Peter

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Oct 13, 2008 at 06:35 AM

    Found the problem

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 13, 2008 at 06:44 AM

    Hi,

    Please check

    Use tcode OVLZ, and double click on your shipping point, delete the loading and pick pack time.