Hi Gurus,

I am working on positive time management and i have few queries:

1. As a consultant I have to suggest my client whether they should for interface between sap and eternal recording system or not... What you guys suggest which one is better.

2. I came to know that there is a standard interface(HR PDC) in sap to interact with ecternal recording system. I want to know how this Sap interact with external recording system i.e. online or offline using this interface.

Please reply to my queries soon..

Points will be awarded for the inputs.

Hope to hear soon from u guys...

Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Oct 10, 2008 at 07:19 AM

    1. As a consultant I have to suggest my client whether they should go for interface between sap and eternal recording system or not... What you guys suggest which one is better.

    If your client wish to go for postive time management it is must for you create interface either you willing to say or not.

    Without that interface you can't do time positive time management

    2. I came to know that there is a standard interface(HR PDC) in sap to interact with ecternal recording system. I want to know how this Sap interact with external recording system i.e. online or offline using this interface.

    I belive this needs some third party tool to intract with PDC. then you have use time evaluation status TMSTA 1 according to PDC

    I belive it bit differnt from what you are looking for.

    please tell me what kind of time terminal your client is using at the moment?

    Best Regards

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 10, 2008 at 01:31 PM

    supriya

    I Belive PDC won't work here, you need to down load inputs from that meachine. Ask you ABAPer to write an interface to upload it to the SAP

    Best Regards

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 10, 2008 at 07:02 AM

    if

    ur ok with interface than i suggest to go with that because if not with this interface u may have some problems while recording from external systems

    we dont have have time recording here i mean positive so jsut want to share my exp

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 10, 2008 at 07:17 AM

    Dear Supriya,

    We have implemented Positive TM recently, I would suggest you to download the Flat file from third party system and write a BDC program to upload it in to Time Events or you can use the RFC which will hit immediately once the employee punch in or out in the third party system.

    I would suggest to go for upload the Flat file daily in to SAP, so that the erroraneous time pair can be identified and rectify immediately to avoid overburden of work. You can schedule the background job to do it regularly in particular time of the day.

    Good Luck.

    Om.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 11, 2008 at 06:37 AM

    Arrange to download the events into a flat file from the time recording machine ( you can schedule a program to do this ) , there is SAP standard program which updates the events from this flat file, the program name is RPTEUP10.

    All you need to do is, put the flat file data in proper format so the program can read and upload events.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 22, 2008 at 03:14 AM

    Hi

    The best way for Positive Time management is to go for an interface with the external Recording system.

    take the output from the external system in a flat file and transfer it into R/3 by a BDC.

    Ravee

    +91.99206.33669

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.