Transport Transfer between vendors

Hi gurus,

we have next scenario: we have stock subcontracting in vendor A. We need to do manipulate this stock in vendor B, but it's necessary to transport stock from vendor A to vendor B. What is the best possibility to do it? The responsible to transport this stock is vendor A.

Thank you, I will give puints!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

6 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 09, 2008 at 09:28 AM

    Hi Daniel,

    Is your individulal sub-contractors have been treated as a seperate storage location attached to any of your plants?

    Regards

    Merwyn

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      "Hi Daniel,

      Is your individulal sub-contractors have been treated as a seperate storage location attached to any of your plants?

      Regards

      Merwyn"

      -- Only exists stock subcontract associated to vendor A and vendor B. Is not a external storage location

  • avatar image
    Former Member
    Oct 09, 2008 at 09:41 AM

    """Hi,

    1.

    If subcontractors are using the same components, you cannot transfer the from one subcontractor's special stock to the other's (standard SAP).

    2.

    If subcontractor1's output (F-30 material) is the input (component) of subcontractor2, you can solve this by specifying subcontractor2 on the delivery address tab of subcontractor1's PO. The goods will arrive to subcontractor2 by mvt 101 + 'O'.""

    -- The second case is not posible. Is not a sequential process. When Vendor A finish his manipulation shouldn't transfer stock to Vendor B until CUSTOMER says it. Can be a lot of days between two steps.

    The first case I don't understand. Can you tell me more please?

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      I repeat, this solution is not possible. When sc-vendor 1 finish material 1, the destiny of this material is not sc-vendor2 always, maybe is sc-vendor3 or sc-vendor4, etc... It's independent things. When you create purchase order for sc-vendor 1, user doesn't know what sc-vendorX will be next step.

  • avatar image
    Former Member
    Oct 09, 2008 at 09:28 AM

    Hi,

    1.

    If subcontractors are using the same components, you cannot transfer the from one subcontractor's special stock to the other's (standard SAP).

    2.

    If subcontractor1's output (F-30 material) is the input (component) of subcontractor2, you can solve this by specifying subcontractor2 on the delivery address tab of subcontractor1's PO. The goods will arrive to subcontractor2 by mvt 101 + 'O'.

    Regards,

    Csaba

    Edited by: Csaba Szommer on Oct 9, 2008 11:28 AM

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 09, 2008 at 09:36 AM

    Hello Daniel

    I feel the second option given by Csaba is the best to map your scenario.

    ie go for the delivery address of the Vendor B in the subcontracting PO for Vendor A.

    You have to just get in touch with the vendor B and enter the GR with movement type 101-O once the vendor B receives the materials from vendor A.

    Regards

    Gregory Mathews

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 09, 2008 at 09:36 AM

    Hi,

    In that case you will need to do the transfer in two steps, first do a MB1B 542 for vendor A and then do a new issue using MB1B 541 to vendor B,

    Transportation charges if any, will need to be met with a direct FI posting.

    Regards

    Merwyn

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 09, 2008 at 10:07 AM

    Hey Daniel,

    From what i think, the only solution is to enter the GR 101 for the F-30 from the vendor 1 and then to issue it to vendor 2 or 3 or 4 by another document with 541.

    No need to receive the physical stock.Once when u get the information about the second vendor and when the stock is is going to be moved, make the receipt for the F-30 material and do the transfer posting simultaneously.

    Regards

    Gregory Mathews