Skip to Content
avatar image
Former Member

Deactivation of Availability Check for an Order Type

We have certain plants which are not relevant to availability check. But due to our order type - the availability check still kicks in!

Can you please let me know the comprehensive settings to deactivate the availability check for a particular order type?

Quick inputs will be highly appreciated (with bonus points 😊 as we need to fix this at the earliest!

Thanks a lot!!!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Oct 09, 2008 at 09:13 AM

    Availability check will happen in your sale order based on your schedule line category.

    So go to VOV6, select your schedule line category for which presently availability check is happening, copy the same and rename it with a new alpha value.

    Now if you execute this new schedule line category, you can see a field "Availability". Untick that box and go to VOV5, select your item category and maintain this schedule line category under the Tab "SchLC".

    thanks

    G. Lakshmipathi

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 09, 2008 at 11:33 AM

    Hi,

    Go to VOV6, un check availability check.

    or follow the path SPRO - SD - BF- AVAL CHECK& TOR - AVL CHK - WITH ATP LOGIC - DEF PROD FOR SCH LINE CAT and go to respective sch line -check if avl chk is ticked or not. if checked remove or unchecked.

    thanks

    guru prasad

    Edited by: guru prasad on Oct 9, 2008 1:43 PM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 07, 2011 at 02:51 PM

    You need to have Z item category & Z schedule line category.. & for this Z sched line category switch off the av check.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 07, 2011 at 05:54 PM

    Hello SAPMAN,

    This is very simple. Avilability check is based on Material master. Go to material master for the plant where AC is not required, then maintain "KP"no check in sales view or MRP view.

    Regards

    Ram