on 10-08-2008 9:22 PM
Hello
1) I have a sales order of non-material stock.
2) Delivery
3) Bill
I want post goods issue mandatory , generating a confirmation service before the bill.
Regards
Cristina
As Rajesh mentioned it is not possible for non stock item.
Try a workaround, if it is acceptable to your business process.
1) Create the material as batch managed.
2) Create a dummy batch for that material using MSC1N.
3) When you are doing delivery system will allow you to save even if batch is not present.
4) When PGI is attempted, system will ask for batch and until batch is given PGI cannot be done.
5) Give the dummy batch number and do PGI.
Test the scenario in SAP.
Regards,
GSL.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For a Non-Stock Material, it is not possible to do PGI. However, Billing is possible without PGI for Non-Stock Item. This is Standard SAP.
Regards,
Rajesh Banka
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.