CJ20N Project Activity Level Actual Dates Auto-Populating

125 Views

Greetings All,

I have a question with regards to t-code CJ20N. Looking at the Activity level of a project, under the dates tab is a field for actual start (AFVGD-ISDD) and actual finish dates (AFVGD-IEDD). They are auto populating and we are not sure why. We do not want these fields to be auto populated. They are messing up resource allocation via CMP3 for us.

I have been looking around and have not been able to find any information on this. Any help is appreitated.

Thanks all!