on 10-08-2008 2:47 PM
Hi gurus
I want create a quota arrangement but only with procurement type in-house Production to use with diferents production versions but when I fill in Procurement type E (In-house production) sytem give me back an error that I can't use this kind of procurement type. what is wrong?
Thanks!!
Hi,
While using the the transaction MEQ1 , just enter the validity dates and go to the item details screen.
There you give both P&S Collumn as E(PROC&SP TYPE) and hit enter . System will not issue any issue message and try to maintain the prodution version and their resective percentage.
Confirm also you maintained the quota arrangement usage in MRP 2 view.
Try and come back
Regards
Pragash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You are right, It works
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.