Pln Ords drop in on a resource, where factory celender is closed

Hi Experts,

I have faced a problem. After heuristic run I found plan ords are getting generated in on a resource where factory celender is closed. for example last twwo weeks of november factory celender is closed in Plant 'A', but heuristic generates Pln Ord there at that time period.

Any clue?

Thanks,

Satyajit

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

4 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 08, 2008 at 03:30 PM

    Hi Satyajit,

    if you have changed the factory calendar recently then you will have to run the report /SAPAPO/CRES_CAPACITY_LENGTHEN.

    Best regards

    Thomas

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 08, 2008 at 03:46 PM

    Hi satyajit,

    How are you doing?

    I don't think heuristic looks at the resource availability.

    Regards, Take care

    Nitin Thatte

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 08, 2008 at 10:37 PM

    Please run the report /SAPAPO/CRES_CREATE_LC_RES

    Also run /SAPAPO/OM17 report.

    Manish

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 26, 2009 at 12:51 PM

    In that(month-end) weekly bucket there was working days..