Skip to Content
author's profile photo Former Member
Former Member

Funds Management - NO AVC check for some Commitment items but Budgeting req

Hi,

For some commitment items like Salary, client wants to do budgeting but without AVC check. So, I cannot create this as statistical item as we need to do budgeting on these CI. Any option to map this???

Thanks & Regards,

Jyoti

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Oct 08, 2008 at 07:44 AM

    Hi Jyoti,

    For this purpose, you could manage tolerance profile and the strategy to derive them. Let's say you define a profile, which says 'do not issues an error, even if the budget is exceeded'. Then, you define a strategy to assign this profile to salary commitment items. Of course, these commitment items should be defined with 30/3 and not statistical.

    Regards,

    Eli

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.