base date not schedule in transaction cj20n, schedule only in CJ21

Friends,

When I try to schedule project dates through the project planning panel through transaction CJ20N, the base dates are not calculated.
When planning through transaction CJ21, planning occurs satisfactorily.
Has anyone ever had this condition?

Thank you
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Apr 20 at 03:40 PM

    What are all your scheduling settings, profiles, and parameters? PS Scheduling is a very complicated process. Please review SAP Notes 151551, 207790, and 700700.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 22 at 09:49 AM

    Ken Melching,

    After analysis, configuration is in accordance with note 151551.
    Please, See the schedule in the attached file
    

    apresentacao1.jpg

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 24 at 01:41 AM

    Ken Melching, thanks for the fast return.

    After reviewing the parameterizations, the dates are not calculated.

    Thanks a lot for the help.

    attached files

    slide1.jpg / slide2.jpg / slide3.jpg

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 22 at 05:49 PM

    WBS Open scheduling there is no hierarchical relationship to WBS dates.

    Look at the configuration that affects scheduling on:

    1. Project Profile

    2. WBS Scheduling Parameters

    3. Network Scheduling Parameters

    All of these setting have to be in alignment. Use the F1 help for how to set the fields. You have to know your scheduling object priority before you make all these settings. Such as, network activities and relationships will set the schedule and the WBS dates will come from them.