SMQ1 SMQ2 - Transfer Preq from ECC to SRM

Hi experts

We are transferring the Purchase Requisition from ECC to SRM , some of them get stuck with error in the SMQ1 and then all the ones created later also get stuck until someone fix the error with the first and then execute the others. I mean, whenever one of the itens get stuck due to some error , all the lines will also get stuck in the Rfc monitor ... My question is :

Is there any way to do not make the lines created later get stuck automatically?

Our monitor QRfc(smq1/smq2) are being full of lines due to one line with problem.

Nowadays we have to go to the RFc monitor and clean the ones with error in order to make the other lines get transferred.

Thanks

Rodrigo

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Sep 05, 2009 at 05:05 PM

    You can not do any thing for the queued recoreds for the queue which got stuck due to a message....

    Only way is to fix the problem and automatically remaining will go through once it got fixed......

    But if SMQ1 queues getting stuck quite frequently then try to clear them once and deregster (SMQR) then regester them again.

    If the problem is sporadic then try to fix the issue .

    Thanks