Hi,experts,
In my equipment BOM, I want to assign material BOM as well as some components also.But I have alternative no for the material BOM.Now, say material bom, X ,alternative no- 1, other alternative is 2,3,4,5,6,7,8,9,10,11,12.Now when I am assigning material bom no X to equipment bom, system is not asking alternative no, it is taking alternative no 1 only by default as when I am opening equipment bom in maintennace order, it is showing the components of alternative no-1 only.Can anybody please guide me how to assign same material bom say X with different alternative no to different equipment no??? please guide me .
thanks in advance.
rgds
rajib
HI
i think we can not have alternative bom for equipments and functional locations.
-ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks dudes
rajib
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
to create equipment BOM
go to transaction IB01
enter equipment number and plant etc
click on copy from Materila BOM
the pop has option to select alternative BOM
are you sure you cannot assign alternative
my system is ECC6.0 but I think this was pretty standard in earlier versions
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ashok
I fully agree with you that equipment and floc BOM do not have alternatives
In my understanding the initial query was
Now when I am assigning material bom no X to equipment bom, system is not asking alternative no
When creating the equipment BOM from a material BOM with many alternatives the system does allow you to assign the correct alternative