Skip to Content
avatar image
Former Member

GR against Purchase order in KAnban

Hi

I have used replenishment strategy as using purchase orders and after maintaining the required elements i made kanban card empty but when i am doing GR against that PO it is not increasing stock neither turning kanban green / full

Please heelp in this regard

Amit

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 06, 2008 at 11:58 AM

    Hi,

    First create one sequence through OM16 transaction.

    Then move to define activity status change then select that sequence and define "Empty --> Full" and activate check box "Action goods receipt".

    Attach this sequence to in ur control cycle then execute it will work.

    It means when ever u change the bin status from Empty to Full then system will do the GR automatically.

    Or

    It will work reverse also like do the GR bin status will changes from "Empty to Full"

    Regards

    Vijay

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      hi vijay

      this is in same regard i mean '+" and '-' sign in kanban

      as u said it will work vice versa it means when i scanning my kanban card from supplier to green / FULL then it would automatically do GR for the same amount as mentioned on the kanban card yse it turns green but negative sign remains there

      and when i do the actual Gr for the PO of that kanban card it then removes negative sign

      I want to avoid this i dont want double process i just want scan to bring material in and that too in desired stock quality stock or some other I mean where i can specify the receiving storage location for external procured part .

      please help in this regard

      Regards

      Amit

  • avatar image
    Former Member
    Oct 06, 2008 at 11:29 AM

    Hi,

    Pls. check the status sequence defined in Control Cycle.

    Whether status sequence is defined for status Empty---> Full or between empty and full any other optional status is defined i.e. transit etc.

    Verify the same and select proper status sequence which fulfills your purpose of status change from Empty to Full.

    Try above and revert back if problem still persists.

    Regards,

    Tejas

    Add comment
    10|10000 characters needed characters exceeded