is kanban with serial number profile for finished and semi finished possible?

Apr 18 at 01:16 PM

76

avatar image
Former Member

because when i am trying to make bin full it triggers the below error

kanban.png

kanban.png (21.2 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

RAJA SEKHARA REDDY BANNURU Apr 24 at 01:13 PM
0

Hi Ramesh
Simulated & Tested the Scenario, KANBAN with the Serial Number profile, for the below Semi Finished Production.

During the KANBAN Status Update to FULL, System is updating the Stock as well as the assigned Serial Numbers, Successfully, at the background. Please take a look of the attached screen shot of the same.

(Material : KANSFG3, Mat.Type : HALB, I n-house Production : PD03 : Working with Planned Orders, Serial No. Profile : YBP1)

Respective Material Master data ( Just for Info)

Inputs/Proposal : Please check the Material Master data setting, with the Serial Number Profile Assignments.. etc)

Kindly let me know, your feedback/comments. Thanks & Regards : Raja


hhima.png (122.2 kB)
vodgm.png (43.8 kB)
Show 6 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Hi,

Thanks. so it is possible.

But i have assigned serial number during production order creation and made full bin , cycle is completed, when i am checking in mb51 document detail there is no serial number picked up. could you send me the ois2 (t-code) detail of serial number profile.

-ramesh

0

Hi Ramesh,

Please take a look of the OIS2 Settings of the Profile : YBP1
Thanks & Regards : Raja

vsdvx.png (35.5 kB)
kanbq.png (39.7 kB)
0
Former Member

control-cycle.pngrepl-strategy.pngsl-profile.png

Thanks, i tried your profile setting but again i am getting same error. I am follwing this sequence, Empty, production order release, co11n confirmation for operation then making FULL bin in PK13N. is it right? -ramesh

control-cycle.png (27.1 kB)
repl-strategy.png (35.7 kB)
sl-profile.png (19.6 kB)
0

Hi Ramesh,
Thanks for the kind & quick feedback.
Hope, you are Testing with some other Material now because, in the beginning, the Error screen shot is shared with the Material # SF-KAN06, Now, the screen shots shared are with the Material # SF-KAN12.
Secondly, you need to follow the sequence of the stages mentioned in flow control from EMPTY>>>> FULL

If you have few minutes of time, please take a look of the below link, to have some idea on the KANBAN Process steps.
https://blogs.sap.com/2018/04/11/kanban-process-in-s4-hana-1709/

Hope, this will helps you, to resolve the reported issue. Thanks & Regards : Raja

0
Former Member

Hi,

Thanks, could you please forward the steps to execute kanban process by stock transfer. i have the requirement for kanban stock transfer from wearhouse to production. both WH and Production are available with in plant.

-ramesh

0

Hi Ramesh
Thanks for the kind feedback
Could you please close this thread, as you already created the new thread for the above question mentioned regarding the Stock Transfer through Kanban from WH to Production. Closing of the issues , with the feedback, will boost the SCN members morale, to provide quick solutions.
Many Thanks for the kind understanding & action. Best Regards : Raja S Reddy