Skip to Content
avatar image
Former Member

Capacity Requirement Simulation from PM Plans (IP19)

Hello,

I need to see the capacity requirements to fulfil our scheduled PM plan obligations (in hours per work centre).

So far I was looking at IP19 which allows you to do something like this but I don't like that you can only see the capacity requirements for work centres specified in the task list. I would like to see it for the main work centre specified in the PM plan.

Any ideas highly appreciated.

Cheers,

Tobi

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Oct 06, 2008 at 08:51 AM

    Tobi,

    What version are you working with?

    The reason I ask is that there is an upgraded version of IP19 in ECC6 (ECC5 too ???). This may give the details you require..

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 10, 2008 at 01:42 AM

    Hi Pete,

    we are still on R/3 4.6c - but I just had a look at IP19 on ECC6 and it seems that it also only takes the work centre from the task list to measure the capacity requirements.

    Regards,

    Tobias

    Add comment
    10|10000 characters needed characters exceeded

    • hi

      you can check in CM50 which will display the workcenter capacity load specified in the operation of the workorder generated through maintenance plan.

      i have check it is displaying both the planned and unplanned .check in the order header whether the capacity is check marked in the dates row

      regards

      thyagarajan