on 10-06-2008 6:21 AM
Hi gurus,
when ever i run CK24 for releasing, it shows 0 MATERIALS, 0 COST ESTIMATE WERE UPDATED SUCESSFULLY.
before that i run STD COST ESTIMATE IN CK11N & save it, it was saved under green light, then
I make a marking in that i assigned a costing varient, that was also done
but when ever i releasing it shows the above message.
pl advice me
thanqu
raj
hi
once the material is estimated and released for the period,
second time for the same period system willnot do estimation.
hi check the reports
CK86_99 Material: Multilevel BOM
CK86 Costed Multilevel BOM
CKAPP01 Materials To Be Costed
-ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
CK 24 and cost estimates can be done for a particular material for that posting period one time only. If you do it again. it will not allow.
Use the same costing variant for CK 24 which is used for CK 11N
Regards
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
i hope you can help me in a costing issue. I made a mass costing with CK40N transaktion in SAP on 07/23 DSCE and TSCE too. Today morning I made DSCE release step and everything its okay with that. Bust, when I am trying release TSCE, SAP do nothing... I am getting a empty SAP screen...:S Could you help me in this case??
my SAP date setting:
costing date from: 08/01/2014 because we have to make a mass costing for our company code 5750....
Hi,
Costing run marking & release to do only once for a period normally for a month. If you release more than once for a month, system will show that error.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
i hope you can help me in a costing issue. I made a mass costing with CK40N transaktion in SAP on 07/23 DSCE and TSCE too. Today morning I made DSCE release step and everything its okay with that. Bust, when I am trying release TSCE, SAP do nothing... I am getting a empty SAP screen...:S Could you help me in this case??
my SAP date setting:
costing date from: 08/01/2014 because we have to make a mass costing for our company code 5750....
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.