costing release

Hi gurus,

when ever i run CK24 for releasing, it shows 0 MATERIALS, 0 COST ESTIMATE WERE UPDATED SUCESSFULLY.

before that i run STD COST ESTIMATE IN CK11N & save it, it was saved under green light, then

I make a marking in that i assigned a costing varient, that was also done

but when ever i releasing it shows the above message.

pl advice me

thanqu

raj

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Oct 06, 2008 at 05:28 AM

    Hi,

    Costing run marking & release to do only once for a period normally for a month. If you release more than once for a month, system will show that error.

    Regards,

    Dharma

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Mangalraj Senthamaraikannan

      Hello,

      i hope you can help me in a costing issue. I made a mass costing with CK40N transaktion in SAP on 07/23 DSCE and TSCE too. Today morning I made DSCE release step and everything its okay with that. Bust, when I am trying release TSCE, SAP do nothing... I am getting a empty SAP screen...:S Could you help me in this case??

      my SAP date setting:

      costing date from: 08/01/2014 because we have to make a mass costing for our company code 5750....

  • Oct 06, 2008 at 05:32 AM

    Dear,

    CK 24 and cost estimates can be done for a particular material for that posting period one time only. If you do it again. it will not allow.

    Use the same costing variant for CK 24 which is used for CK 11N

    Regards

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hello,

      i hope you can help me in a costing issue. I made a mass costing with CK40N transaktion in SAP on 07/23 DSCE and TSCE too. Today morning I made DSCE release step and everything its okay with that. Bust, when I am trying release TSCE, SAP do nothing... I am getting a empty SAP screen...:S Could you help me in this case??

      my SAP date setting:

      costing date from: 08/01/2014 because we have to make a mass costing for our company code 5750....

  • avatar image
    Former Member
    Oct 06, 2008 at 05:34 AM

    hi

    once the material is estimated and released for the period,

    second time for the same period system willnot do estimation.

    hi check the reports

    CK86_99 Material: Multilevel BOM

    CK86 Costed Multilevel BOM

    CKAPP01 Materials To Be Costed

    -ashok