Shipping Instruction set as default but not asigned in MIGO

Hi expert, we are using Shipping Instruction for vendor evaluation, we have set Shipping Instruction as default in customiz, but when you are making GR in MIGO the field is not asigned to the variable, is just suggested in the screen.I get a error ME112.

Is that the standar behaviour? Is there any option (user exit, etc) to get the default value whitout confirming Shipping Instruction ?

Thanks again!!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Oct 06, 2008 at 01:03 PM

    Thanks Narayana, I did that too, the Shipp Instr. comes ok with the material using Pur Val Key, but it comes just like a suggestion, the problem is that I have to confirm every single line item, the program seems not to assign the value until I check the Shipp Instr.

    Is there anyting to make it without checking? Regards

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      This is the SAP standard function that you have to select an select an instance of compliance with shipping instructions.

      From configuration, system will automatically select the already configured score but user has to confirm the score during GR in MIGO. Also if he wants to make changes in the score he can change it.

      If you want to have a fixed score for vendor and don't want to allow user to select any other score then better maintain only one score for the shipping instruction in configuration so user has to select that score only.

  • avatar image
    Former Member
    Oct 06, 2008 at 01:30 PM

    Ok, I will try with an exit then, I need the suggested value to be taken, but allowing in certain cases to be changed, Thanks.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Guillermo,

      I'm facing the same problem, i want to give the same "compliance with shipping instructions" for all items.

      I wonder if you can identify the exit that you used? You have used any button to replicate the compliance for all items?

      Thanks

  • avatar image
    Former Member
    Oct 06, 2008 at 07:47 AM

    Hi,

    Have you assigned the Shipping Instruction defined at SPRO (with details of 'Compliance with shipping Instructions'-Points) to the Purchasing Value Keys at SPRO.

    If not, please go to the Purchasing Value key (Specified in your material master record) in SPRO -> Materials Management -> Purchasing -> Material Master -> Define Purchasing Value Keys -> Here, assign the already defined Shipping instruction to the related Purchasing Value Key.

    Now, try to do the GR ( for the material, to which above Purchasing Value key is assigned) in MIGO. The system will ask you to select the Compliance with shipping Instruction.

    Hope, it helps.

    Regards,

    Narayana.