on 10-04-2008 3:24 PM
Hi everybody;
How can I go from AFRU table to MSEG table? (BLPP doesnt work in production order, it works for only REM)
Hi Emre,
AFRU-WABLNR = MSEG-MBLNR
If AFRU-WABLNR is empty:
AFWI-RUECK = AFRU-RUECK
AFWI-RMZHL = AFRU-RMZHL
AFWI-MBLNR = MSEG-MBLNR
...
Regards, Andreas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Link is as below
AFRU-AUFPL = CAUFV-AUFPL
from here you will get the order number - AUFNR
CAUFV-AUFNR = MSEG-AFUNR
I hope you got the link.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Emre,
I'm a bit confused. By your initial question I thought you are working with production orders. But now you say that you use MFBF and COGI only.
For production and process orders there is no other 1:1 relation between AFRU and MSEG than given above in my previous response:
AFRU-WABLNR = MSEG-MBLNR.
If there's more than one document per confirmation, also table AFWI is used, but for production/process orders only (not for REM).
Hope it is clear now.
Best Regards,
Andreas
Edited by: Andreas Seibel on Oct 9, 2008 8:54 AM
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.