I am creating maint plan (IP42) and during assigning Task List, it is asking for "Task List Type" as input.

I have searched in header screen of task list but could not find it. Can anyone say from where I can get this.

Regards.

Manoj

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Oct 03, 2008 at 10:49 AM

    Hi manoj,

    Enter task list type as ' E '

    And enter group and group counter from task list header screen

    Amol

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 03, 2008 at 10:50 AM

    Hi Manoj,

    What type of task list you have created.

    If it is General Task list, then the Task list type will be

    A - General maintenance task list (It get created through Trx IA05)

    If it is Equipment Task list, then the Task list type will be

    E - Equipment Task List (It get created through Trx IA0A)

    Regards,

    Shyamal

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 03, 2008 at 11:58 AM

    HI

    at the time of creating plan, youhave to assign the task list,

    so when you search from plan you need to tick on check box of FL tasklist (if plan belongs to FL level),tick equipment task list if you want to assign the task list created against the equipment(IA01)

    if you want to assign the general maintenance task lsit tick on the check box of general maintenace task list.

    if you want to know the task list type

    A -general task list

    E-Equipment Task List

    T-Task List for Funct. Location

    -ashok

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 04, 2008 at 05:32 AM

    Dear,

    You are creating Strategy plan and in this task list which you are assigning should have strategy.

    When you go into task list header there the is field strategy, in that enter any strategy. Now this task list can be used for IP42.

    Regards,

    Kaushal Rai