Hi All,

I have a question about the Excle Add-in and the planning view.

I want create a telescope planning view in the excel Add-in. That means, that the first 8 weeks can planned in weeks (the first 2 months) and the rest of my planning horizont can planned in month. In APO DP it was possible to create a interactive planning view, which consider this telecoping planning. Is this also possible in IBP with the Excel Add-In ?

Regards

Oliver

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Oliver Richter Apr 17 at 07:49 AM
0

Hi,

if I click the send button i found the soultion.

filter -> time horizont -> add period

Share