Dear PP consultant,

I have tried to force close for the production in partially delivery. We have done correct procedure for force to close the production order. We are using this t-code: COHV,select mass processing in technical completed, enter the production order, F8, hight light the production order and finally click mass processing then status will appeared on the screen teco.

After we have ran the WIP report. The production order still appeared on the WIP report. Why? We don't expect the production order again appeared on the WIP report. Kindly guide me ASAP.

Regards,

Krishnan.