Some of my Crystal reports need caching and some are run so frequently that they need caching set to zero.

Is there a way to have certain reports use a different cache server?

Thanks,

Todd

Edited by: Todd Stalie on Oct 2, 2008 11:01 PM

Edited by: Todd Stalie on Oct 2, 2008 11:02 PM

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 02, 2008 at 09:15 PM

    Yes.

    Create 2 Server Groups, each with one cache server. When scheduling the reports, you can choose which server group processes the report.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 26, 2009 at 04:26 PM

    Turned caching down to one minute, seemed to resolve the issue well enough.