04-17-2018 5:14 AM
I was using schedule once option with API to schedule a webi report. And I passed current date/time for startdate & enddate was some random date in future .
SAP BO server is set up on UK locale machine.
Before DST the schedule was executing at the scheduled time, but after DST it's running after 1 hour.
Is this a known issue / what is the fox for the same.
04-17-2018 4:34 PM
Hey Tarun,
can you have a look at below KBA:
1448881 - Multiple instances spawned after daylight savings time change
-Kedar