I was using schedule once option with API to schedule a webi report. And I passed current date/time for startdate & enddate was some random date in future .

SAP BO server is set up on UK locale machine.

Before DST the schedule was executing at the scheduled time, but after DST it's running after 1 hour.

Is this a known issue / what is the fox for the same.

API
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Kedar Kale
6 days ago
0

Hey Tarun,

can you have a look at below KBA:

1448881 - Multiple instances spawned after daylight savings time change

-Kedar