cn41n-report.pngHello ,

in CN41N Report Column " Later " is showing wrong data.

On activity level it was fine, but Network level, WBS and Proj, Defi. Level it goes double.

Need guidance.

Thanks,

Akash Khandelwal

+91-8128357194

akashkhandelwal368
Active Participant
0 Kudos

Hi,

I have done one change from Aggeragated value to Non-Aggregated , so data are coming perfect on network and activity level, but no data on wbs level inspite wbs is already confirm.

Can anyone guide me for same. Or any one can give me any other method to review project status on date basis

Accepted Solutions (1)

Accepted Solutions (1)

akashkhandelwal368
Active Participant
0 Kudos

Problem Solved :

I made changes as per below and without clicking on Non Aggregated ;

Include : RCNSOFST

FORM : GET_NETZKO_STRUC

At line 862 inserted statement CLEAR G_STRUC-SPAETER.

Hope it is help to other.

Thanks,

Akash Khandelwal

Answers (1)

Answers (1)

kenmelching
Active Contributor
0 Kudos

Please review SAP Note 207790 for detailed description of Later calculations. If there is still confusion you will need to submit an SAP Incident.

akashkhandelwal368
Active Participant
0 Kudos

Hi,

I have done one change from Aggeragated value to Non-Aggregated , so data are coming perfect on network and activity level, but no data on wbs level inspite wbs is already confirm.

Can anyone guide me for same. Or any one can give me any other method to review project status on date basis

kenmelching
Active Contributor
0 Kudos

Submit an Incident to SAP.

akashkhandelwal368
Active Participant
0 Kudos

Raised to SAP, SAP replied that it is standard behavior.