Skip to Content
avatar image
Former Member

copy material from one plant to another

please help me. how to copy all materials from one plant to another. is there any transaction code available?

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

7 Answers

  • Best Answer
    Oct 01, 2008 at 09:15 AM

    Dear,

    Use MM01 and use the "Copy From Material" template. The next screen will ask you to enter from which plant to which plant. If this screen does not appear, click on "Organizational Levels" in the first screen.

    You may notice that all of the fields do not get copied. Besides choosing the views you want, this could be because you did not enter all of the information in the organizational level screen. Be sure you enter the company from, the company to, the plant from, and the plant to as well as the Sales organization

    Another important step is that you need to set up the defaults >>> views and, most importantly, the defaults >>> organizational levels in MM01 before you start the copy. You need to set up all the views you want to be created, and then all the fields in the "Copy From" column which are relevant, because it will not copy data into views which are controlled by this data if it is missing. For example, if you do not specify the sales organization and distribution channel, it will not copy data into the sales views.

    Or refer this link,

    http://sap-img.com/abap/bapi-to-copy-materials-from-one-plant-to-another.htm

    Regards,

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 01, 2008 at 09:13 AM

    Hi

    This is possible with the help of BDC Programe.

    Transaction code -MM01

    Vivek

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 01, 2008 at 09:16 AM

    hi

    Coying material from one plant to another is called extending of material .

    tcode is MM01.

    Enter the material code of the material code you want to extend.

    In that enter the plant from which you want to copy to, and from which plant copy from.

    Regards,

    vijay

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 01, 2008 at 09:16 AM

    since you are talking of all materials,then the best possible way is to contact with your ABAPer and go for a BDC programme.

    regards,

    indranil

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 01, 2008 at 09:32 AM

    Use MM01with Copy From Functionality.

    Go to MM01 Input Old Material Number in Copy from field and in Organizational Level Old Plant number and Stor Locn in Copy from Fields and Extend the Material to new Plant & Storage Locations

    If Material is Bulk Better to Use MM01 with LSMW

    Else Go for BDC

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 01, 2008 at 09:35 AM

    Hello

    Since you want to extend all the material from one plant to another, use the program RMDATIND. It is for the direct input of material masters.

    Also consult your abaper for doing this.

    Hope this helps

    Regards

    Gregory Mathews

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 01, 2008 at 09:11 AM

    Dear,

    You can extend material from one plant to other plant with MM01 t-code.

    Enter MM01 t-code, Enter material code in Copy from field and material code filed.

    Then press enter, Select view.

    Enter plant and storage location in Copy from(From which you want to copy material)

    Enter Org. level plant and storage location data fro where you want to

    copy material.

    Then just click on all view and save.

    Regards,

    Mahesh Wagh

    Add comment
    10|10000 characters needed characters exceeded