Minimizing Downtime during Upgrade

Hi All,

We are in process of upgrade from R/3 4.7 EE 2.00 to ECC 6.0 SR3.

The details of legacy and new landscape is as follows :

Legacy Landscape

OS Solaris 9

DB Oracle 9.2.04

SAP R/3 4.7 EE 2.00

New Landscape

OS Solaris 10

DB Oracle 10g

SAP ECC 6.0 SR3

We have taken the offline backup of Live PRD and restored it on to Stand by server. We have also upgrade oracle 9i to 10g, which has taken around 20 hours.

My question is, we want to minimize the downtime by directly installing Oracle 10g with R/3 4.7 EE and the take the offline/online backup of live PRD system and restored back to oracle 10g enviroment. By doing this we can reduce the downtime by aprrox 15 hrs.

Is this scenario is possible ? Please give your valuable suggestion from your last experiences.

Thanks,

Kshitiz Goyal

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Oct 01, 2008 at 12:51 PM

    > My question is, we want to minimize the downtime by directly installing Oracle 10g with R/3 4.7 EE and the take the offline/online backup of live PRD system and restored back to oracle 10g enviroment. By doing this we can reduce the downtime by aprrox 15 hrs.

    Yes - this is possible.

    I suggest you get the newest installation CD set for 4.7 which supports Oracle 10g (using sapinst, not R3SETUP):

    See note "969519 - 6.20/6.40 Patch Collection Installation : Oracle/UNIX", Section 3:

    3.) Retroactive Release of Oracle 10.2

    Markus

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      Do not do use a backup/restore use the R3load export/import database independent method for the system copy.

      As you will be changing the database release 9i to 10g - the backup/restore procedure is not supported.

      Hope this helps.

      - Regards, Dibya

  • author's profile photo Former Member
    Former Member
    Posted on Oct 12, 2008 at 04:20 AM

    Hi,

    I would suggest to split your SAP upgrade on 2 weekends. One weekend you do Oracle upgrade and another weekend, do SAP upgrade.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.