Is there any way to fix one of the material component costs in standard costing ?

Former Member
0 Kudos

Please help ! Thanks.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Rajendra,

Please provide the T-code and if possible, screenshots for the steps.

Thank you !

Regards,

Ambrose

Former Member
0 Kudos

Dear Ambrose,

You have to maintain the Item Valuation method available in Inventory Tab as "Standard" and mention the Item cost price required in the header field for Item Cost. The same or requirement Item cost can also be maintained on the Warehouse level for a particular Item Master.

Best Regards,