hi friends,

i want to know what impact the operation has when i use control key PP04-Routing - in-house prod. with check.

i am including quality inspection operation after every operation. so when quality department approves it does it create any inspection lot or what is the exact thing which has to be done to carry on to the next operation.

pls guide

sanju

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

You can use Control Key PP04 in which inhouse production with Inspection Check.

Make the setting in the control key inpsection charactertics required and confirmation required for that operation.Generate the inprocess inspection lot with inspection type 03 in the material master.

Do inspection result recording and confirmation for the operation from Qe11.But do not forget the to give the inspection point in the routing and go ahead.

Regards,