on 09-30-2008 9:15 AM
Hi Experts,
I have changed a holiday in a factory calendar to be a working holiday in a particular plant. Could you please help me how could i test if this is working. I've tried to create a process order for that day but the system is still prompting a warning message that that day is not a working day.
Please help.
Thanks, thanks
Dear Ellen ,
U can achieve this by using Special Rule functionality .OP03/SCAL is the transaction code. Click the Maintain button then select the Factory calendar radio button and press the change (pencil) button. Select your calendar then press the change (pencil) button again. Click on the Special rules button then the Create button (paper). Enter the From and To date(s) [same date if only one day] then if it WILL be a work day check the Workday field and you will need to enter Text.
If, for example, the day is a normal workday and you want to shut down for that date (or date range), this time leave the Workday check box empty. Click the paper button when you're done entering the data then the save button (or the F-11 key). You're done. This is configuration data therefore configuration for OP03, SCAL and SCA6_U must be allowed in your profile.
Now goto OP03 again and reassign the Plant to that calander and also check at work centre level whether the same calander re-assinged or not
Hope this will clear your idea
Regards
Jia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Could you please tell me how you did the change in factory calendar?
I go to change option but I am not able to change it.
Please advice
Regards,
Aravind
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi!
You can try like this: in change mode of factory calendar you choose Special Rule and create a working day on ur pulic holiday.
Hope it ca solve ur problem.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
When you create Holiday Calander no transport request is automatically generated.You need to go to Calander -> Transport (F8) to generate the transport request to respective server.
You have to assign factory calendar to PLANT
Go to SPRO>ENTERPRISE STRUCTURE->DEFINITION> LOG GENERAL>DEFINE COPY,DELETE AND CHECK PLANT>DEFINE PLANT
Please note that the check Factory calendar changed and maintained in plant or WC is same or different.
After doing the chnage when you click on F4 on any date field, system showes holiday or working day?
So go in work center in capacities screen define your interval of avilable capacity there, you will get option workdays there you have to select :- Working days (overrides factory calendar). Meas all days are working day.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.