Reg:No Reqmts/Caps exists or not relevant to finite scheduling

Dear PP Team,

When I release the production order, the following the error message came:

No Reqmts/Caps exists or not relevant to finite scheduling.

Regarding that i checked with workcenter which have all details of Finite scheduling indicator in Capacity view.

Pls suggest me what is the solution for that issue.

With Regards,

P.Arunkumar.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Sep 30, 2008 at 06:32 AM

    Dear,

    Have maintained the active vesion of capacity in the capacity header screen of work center?

    Maintain scheduling parameters of ur order type in OPU3 and OPU5 with active tick mark for scheduling and capacity generation.

    Check in the operation control key wheteher determine capacity reqmts indicator has been enabled.

    Also check whether you have assigned the right formula's in the Capacity and Scheduling Tab of the work centre

    Regards,

    R.Brahmankar

    Edited by: R Brahmankar on Sep 30, 2008 12:08 PM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 30, 2008 at 06:40 AM

    HI

    also check the formulae defined in capacity.

    -ashok

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 30, 2008 at 06:48 AM

    Hi

    1. Check Scheduling parameter for Production order (OPU3).

    Select Scheduling & Generate Capacity Requirement.

    2. Also check Scheduling for Plan order (OPU5)

    Here also select Scheduling & Generate Capacity Requirement.

    3. Also check control key.

    4. Also check formula for Capacity & scheduling in Work center.

    Thanks

    Ashish