Factory Calendar to Calculate Nextworking day

Hi Gems,

i am having Factory calendar with Current date as User Selected

Date.

Next working date = user selected date+3.

3 days should not include holidays and weekends .

factory calendar type is US.

Regards

Bhuvana

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Sep 30, 2008 at 08:34 AM

    END_DATE_DETERMINE

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 01, 2008 at 03:55 AM

    Hi Bhuvana,

    There's a method available Factoryget* something of that kind. It will take the Country into consideration and will populate the next date accordingly which will not include the holidays. I've used that method for some requirement arnd 2 yrs ago, hence not able to remember exactly....

    Cheers,

    Santosh Verma,

    Deloitte, India.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 13, 2008 at 10:37 AM

    Solved.