Rough Cut Capacity Planning

0 Kudos

Hi,

SAP Gurus,

Can anybody give me the required configuration setting and step by step procedure for rough cut capacity planning.

Thanks and Regards,

Harriesh.

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

In OP45 , pls ensure that for the usage,task list type 3 (Rough cut planning profile) is included is only required confiuration setting.

1- Create Rough cut planning profile - MC35. Enter material and plant nd execute. Enter status = 4, usage = 1.

Enter a resource name and double clik on that line, choose Example work centre: Enter work center name, plant and unit = H.

Enter the times required in Hours in the time buckets and save

2-Create SOP plan - MC87. Enter material and plant. Execute. Enter sales and prod qty. Go to views>Capacity situation>Rough cut planning>show.

3.In mc82, go to views->capacity situation->show

You could display the capacity requirements at the bottom of the screen.

Refer this link,

http://help.sap.com/saphelp_46c/helpdata/en/8a/a5905c4adc11d189740000e8322d00/frameset.htm

Regards,

R.Brahmankar

0 Kudos

Dear,

Is it possible to do rough cut capacity planning without SOP. Please let me know. Please give me stages.

Thanks and Regards,

Harriesh Gunjatay.

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Not possible then go for capacity planning with order management.

I have already explain you details about rough cut plaaning.

The follwoing information given by sap will be useful.

help.sap.com/printdocu/core/Print46c/en/data/pdf/PPCRPSOP/PPCRP_SOP.pdf

help.sap.com/saphelp_45b/helpdata/en/a5/63211443a211d189410000e829fbbd/frameset.htm

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi

Pl clear my doubt.

You mentioned "Enter the times required in Hours in the time " (mc35) in this which time we should enter.Can you pl elaborate.

Regards,

Raj.K

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Here we check the capacity for our bottel neck work center. So you have to define time for your materail requried to manufacture certain quantity on this work center . Ex-enter the time to produce 1 pc

Create Rough cut planning profile - MC35. Enter material and plant nd execute. Enter status = 4, usage = 1. Enter a resource name and double clik on that line, choose example work centre: Enter work center name, plant and unit = H.

Enter the times required in Hours in the time buckets and save

Hope clear to you.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi

Thanks for your reply.

What should I enter in Field Time span ? It is in work days.Rest part is clear

Regards

Raj.K

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Time span --Specifies the time frame in which you view resources in a rough-cut planning profile.

Generaly we use to plan for 1 month so we define there as 30 days.The time span is measured in workdays. And then work center time requirement as an Hrs.

Hope it will claer your doubt.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi

Thanks a lot. You cleard all my doubts .

Regards,

Raj.k

Edited by: rajaram kulkarni on Oct 22, 2008 7:00 AM

0 Kudos

Dear,

All

Thanks for reply.

Regards,

Harriesh.

Former Member
0 Kudos

This message was moderated.