Hi experts,

I am in to a new implementation project on s/4 HANA 1709. in my client place I have configured different leave quotas both pro rata & no pro rata basis. while running time evaluation on PT 60 (Pro rata basis) day balance is getting created with respect to the current date starting from start date. But I have put start date & end date as 01.04.2018 & 31.03.2019 respectively. But instead of 31.03.2019, time evaluation is running up to current date i.e as of 16.04.2018. I m getting confused, any body who would clear my confusion.

Thanks,

Sudhansu

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Brendan Gibbons Apr 16 at 08:07 AM
0

Hi,

Unless you have specifically coded in your schema to do so, PT60 will only evaluate and store results up to todays date.

Some of the standard schemas will process into the future but will only simulate the future and not store results to the cluster.

bg

Show 3 Share
10 |10000 characters needed characters left characters exceeded

Thanks Brendan. Now I am clear..The base entitlement will get prorated day by day & quota will begenerated up to date. Thanks again.

0

Now I am able to see all my quotas (PL-20days Pro rated) & CL-10 days & SL-10 days both No pro-rata basis) . But in my quota generation screen I m getting this amount. CL-showing 10 days but SL-showing 3650 days in SE 38, RPTQTA00. Why...? I have attached my screen here, please look in to this.

0

1 - I can see no "screen" attached.

2 - Since your initial query was answered, you should create a new one for this question, with an appropriate title. Also provide more information on your configuration and on the employee being processed (original quota contents, period being evaluated, etc.). Screen captures can also be helpful.