Automatic deletion of Production version and routing?

Apr 14 at 09:15 AM

54

avatar image

Hi Gurus

Production order TECO is done with COHV during these production version and routing is deleted automatically.still I can't able find the reason for deletion.still looking solution to this.

Thanks in advance

Note:

Deletion of routing I can bale to see at CA02 and CA03 by inputting group number and Plant not with material number,plant.

Is any possibilities Malfunction while executing COHV (deletion of production version and routing).

matnr-werks.png (37.2 kB)
plpo-werks.png (19.5 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Caetano Almeida
Apr 18 at 01:41 AM
0

Hello

There is no such feature in the standard system.

If the routing and production version are being deleted when completing the order in COHV, this is definitely a custom development.

You can try to run a take in transaction SE30 when running COHV, in order to find out which custom programs are executed.

Regards,

Caetano

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Thanks Ceatano

I will check the same and Come back to you for further requirement.