Class charac.is already linked with master insp. charac.TEMP1 in plant 0001

316 Views

Hi.

Please help me with my problem.

I try to link class charac. "TEMP OIL" with master insp. charac. "TEMP2" in plant 0002.

Also class charac. "TEMP OIL" linked with master insp. charac."TEMP1" in plant 0001.

And as a result I have system message:

"Class charac. is already linked with master insp. charac. QM_TEMP in plant B801

Message no. QS094

Diagnosis

You want to link a class characteristic that is already linked to master inspection characteristic QM_TEMP in plant B801 to another master inspection characteristic. This is not allowed, since each class characteristic can only be assigned to one master inspection characteristic.

Procedure

Assign a different class characteristic, or no class characteristic to the master inspection characteristic."

But I can't assign a different class characteristic because we inspect the same material in different plants. And the same material have the same class characteristic in all plants. Also I should create for each plant for one master insp. charac, because they are define on each plant.

Where is the escape?

Thanks, Maria.