Rounding Value in Planned Orders

Hi All,

I have issue with Round Value. My planning strategy is 40. Using procurement type E. My lot size is MB. I have maintained Min Lot size 5,700 and Max Lot Size 39,600. I have kept Rounding Value as 1,000. PIR requirements is 4,000 per month

When i do MRP run, system is generating Planned Orders of 5,700. Is this right? If yes could you please explain me.

Is Rounding profile is mandatory?

Thanks & Regards,

Ramesh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Apr 16 at 02:57 PM

    Hello

    This is a standard system behavior, explained in the following consulting note:

    49663 - MRP: Rounding and minimum/maximum quantity

    In order to avoid this issue minimum lot size should be maintained as a multiple of the rounding.

    Regards,

    Caetano