Dear Experts,

I have a material with 150 days of planning time fence with MRP type as P3 and lot size as WB.- as mainitan in material master.

But in MD04 End of planning time fence is showing around 180 days from today date

So pls tell me what are the factors affecting to determine the end of planning time fence in MD04 other than the date maintain in material master

Faisal

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
RAJA SEKHARA REDDY BANNURU Apr 15 at 04:41 AM
0

Hi Faisal,

For the Planning Time Fence, System will consider the only No. of Working days.
In the mentioned case, it will consider 150 Working days from Today's date. If there any holidays, in-between, those no. of days will get added up. This is the SAP Standard behavior. For Planning Time fence, the system will consider that many no. of working days, from today's date( Not the Calendar days). Please check you Factory Calendar, to know the details of the Holidays/non working days.
Hope, this is Clear. Kindly let me know if you need any further assistance, else, please close this thread.
Many Thanks & Regards : Raja