Hi all,
While i conform the SD billing the system is displaying the following message...
The Material belong to 3000 plant.
No standard cost estimate could be found for material "11120DAL0"
Message no. K/834
Diagnosis
In Profitability Analysis, an attempt was made while valuating with material costing to read for material "11120DAL0" a standard cost estimate released on posting date "28.09.2008".
The system has discovered that there are no error-free standard cost estimates released in plant "2000" on the specific date "28.09.2008" for material "11120DAL0".
The material cost estimate is accessed according to the CO-PA Customizing settings for costing key "001" under Define Access to Material Costing.
Display Cost Estimate for Material
Display Material Cost Estimate without Quantity Structure
System Response
It is not possible to process the document further.