I would like to implement a solution that from xxxxxxxxxx order number the rules defined in procedure shall be applicable. Can we use the object field VBELN in procedure syntax?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Dhandapani Satheeshkumar Apr 14 at 12:30 PM
0

Hello Deppak,

VBELN is for Sales Document number so which table are you trying to go fetch it from, in case if you like to read this from the VBAP Table, then you need to know that the VBELN will be filled after save only. So if this will be ok for your rule then you can use the reference characteristics function and meet your requirement.

Br,

DsK