Problem in Release PO in ME29N

Former Member
0 Kudos

Hi,

Once the PO is created, the release strategy is affecting the particular PO, but when the Client try to release in ME29N Transcation the system is not allowing.

System is allowing to release in ME28 Transcation.

Any configuraiton is missing or where to check.

Pls guide me.,

Accepted Solutions (1)

Accepted Solutions (1)

kunal_ingale
Active Contributor
0 Kudos

hi

ask ur basis person

he might not have autherity to use me29n

regards

kunal

Answers (2)

Answers (2)

Former Member
0 Kudos

What I have found is that you must have change authority (ME22) to execute the release in ME29N. This has been a problem for our auditors so I am trying to find out if there is a way to use ME29N only for release (not allow any changes to the purchase order). Right now the only thing I find is that you have to use a user exit to do this.

Former Member
0 Kudos

Sharon,

Did you find a solution for your requirement? I have a similar request from my client as well. Any tips would be helpful. Thanks in advance!

- Jeff

Former Member
0 Kudos

Dear,

Enter ME29N t-code, If system give message you have no authorization for t-code, Then contact with Basis person.

Otherwise check in purchase order release strategy is effected ot not

Regards,

Mahesh Wagh

Former Member
0 Kudos

Hi,

Release Strategy is affecting the Puchase Order and the client can able to release the same purchase order in ME28.

Former Member
0 Kudos

Hi,

Please tell me any error occur at the time of release purchase order with ME29N.

Please mention error message or more detail regarding issue.

Regards,

Mahesh Wagh

former_member192897
Active Contributor
0 Kudos

It Seems an Authorization Issue. Please tell you client / User to execute trxn code ME29N if it throws any message then just tell him to enter /NSU53 in the same trxn code command box. System will take you to SU53 and show the Missing Authorization Object..