Hi PP gurus,
I have two Finished Goods under a same plant, both of them have the strategy 40 (planning with final assembly). Both have ZERO stock. Two SALES ORDERS are created for both Materials. However when i run MRP per PLANT. Only the FIRST Finished Good have PLANNED ORDERS created, the second one does not.
What could be the setup that i miss that could cause. We want to have planned orders created if Sales orders have been created and the materials has zero stock.
I would greatly appreciate if someone could help me.
Thank you,
Heinrick Palad