on 09-25-2008 7:00 AM
Hi Gurus,
my client is having mto scenario.
after running MRP .PR(for sub contractor) is generated.
while adopting to create p.o system giving following error.
"Combination item category L/account assignment category M not defined"
Message no. ME066
pls clarify me how to solve this error & give some information relating to account assignment M.
Thanks & regards
venkat
> "Combination item category L/account assignment category M not defined"
> Message no. ME066
Go to SPRO-MM-Purchasing-Account Assignment-Define Combination of item category L/account assignment category and Maintain Combination for Acct Assig M with your Item category & Save.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Maintain combination of item category & account assignment in OMG0 of your requirement.
Regards
Ravi shankar.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Go to OMG0 and assign item category L and account assignment category M.
This will help
Regards
Gregory Mathews
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi all,
Thank you for all its working.
thanka & regards
venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Goto SPRO > Materials mnagement > Purchasing > Account assignment >Define combination of Item category/ Account assignment category
Define here your combination.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.